In late 2020, Precision was awarded the prime contract to construct substantial site improvements at one of SoCalGas’s regional service facilities. The scope of work included removal/replacement of A/C paving, removal/replacement sections of failing retaining walls, removal/replacement of insufficient sub-base materials, installation of new concrete slabs to accommodate on-site fuel tanks, installation of bollards, parking signage and wheel stops, striping, security gates and fencing, as well as installation of new landscaping and irrigation throughout the multi-acre site. The roughly $2 million project was completed in spring 2021.